A campaign is a run of same-product tasks on a machine between two changeovers. Typical rules:

  • tasks within a campaign are the same product and pay no changeover cost,
  • a campaign has a maximum size (e.g. at most N tasks),
  • switching products or hitting the cap triggers a changeover.

Approach 1: campaigns as entities

Create a set of potential campaigns, each with start/end/duration/presence, and variables linking tasks to campaigns. Sequence campaigns (not tasks) using add_circuit. The campaign-level changeover cost sits in the gap between campaigns.

Pros: close to the business view. Cons: more variables, scales worse.

Example: example_09_max_number_of_continuous_tasks.py.

Approach 2: cumulative rank per task

Keep tasks as the atomic unit and attach a rank variable cumul[t] in [0, campaign_size - 1]. On each t1 -> t2 arc:

  • if the campaign continues, cumul[t2] = cumul[t1] + 1,
  • if a changeover happens, cumul[t2] = 0 and end[t1] + changeover <= start[t2].

A reach_max[t] boolean fires when cumul[t] == campaign_size - 1, forcing a reset and changeover. add_max_equality(max_value, [0, cumul[t1] + 1 - reach_end[t1] * campaign_size]) is a useful trick to compute the next rank under an only_enforce_if.

Pros: fewer variables, scales better. Cons: trickier to explain.

Examples: example_24_campaigning_with_cumul.py (base), example_27_campaigning_products.py (multi-product), example_28_campaigning_products_machines.py (multi-machine).

Locking the task order

When tasks have deadlines that align with their index, locking start[t-1] <= start[t] (or the stricter end[t-1] <= start[t]) is a cheap heuristic that often gives a 10x+ solve-time improvement. See example_25_campaigning_with_locked_seq.py and the two example_26_campaigning_locked_seq_improved*.py variants.

Flexible campaign ends

If the model should be free to end a campaign early (not just at the cap), drop the "force reach_end when cumul hits max" implication and let the solver choose. This usually gives better objective values at a small solve- time cost. See the two example_26_*_improved*.py files for the comparison.